Your customer executes deadline monitoring (transaction IP30). What happens after you insert additional call dates using the manual call function? Please choose the correct answer. Response:
A. The system restarts the maintenance plan. B. The system retains the normal scheduled call dates. C. The system fixes the next scheduled call date. D. The system reschedules all previous scheduled call dates.
Answer: B
Question: 2
Your customer wants to settle costs of the refurbishment process to an inventory account. What Customizing does the process require? There are 2 correct answers to this question. Response:
A. Special control keys for use in refurbishment operations B. A specific order type for refurbishment processing C. A specific settlement profile for the purpose of refurbishment D. A specific notification type for refurbishment processing
Answer: BC
Question: 3
You have selected Confirmation Required in the control key for operations in a maintenance order. One of the operations is already partially confirmed. Which system statuses can the order header display before all operations are finally confirmed? There are 3 correct answers to this question. Response:
A. TECO B. PCNF C. CRTD D. CNF E. CLSD
Answer: ABE
Question: 4
Your customer wants to utilize estimated costs in Plant Maintenance orders. Which condition does the customer need to be aware of? Please choose the correct answer. Response:
A. Planned costs overwrite estimated costs after release of the order. B. A specific order type in which cost estimates are activated must be used. C. Planned costs must not exceed the estimated costs. D. Upon release of the order Cheap Darnell Nurse Hoodie , estimated costs cannot be revised.
Answer: D
Question: 5
What are the 2 options available for archiving order? There are 2 correct answers to this question. Response:
A. Manually enter historical orders B. Recognize orders. C. Order settlement D. Refurbishment E. Copy orders
Answer: AB
Question: 6
In order costing Cheap Patrick Maroon Hoodie , what is the allocation structure used for? Please choose the correct answer. Response:
A. To provide a hierarchy structure for posting costs to the general ledger B. To provide a structure to summarize postings across cost elements C. To determine the cost element for debit to the order and credit from the order D. To determine the overhead costs that need to be applied to each cost element
Answer: C
Question: 7
Find out the elements responsible for performance management. There are 3 correct answers to this question. Response:
A. Investment planning B. Project definition C. Execution D. Dispatch E. Ordering
Answer: ABC
Question: 8
What do you need to select when you create a maintenance plan that only generates notification(s)? Please choose the correct answer. Response:
A. A maintenance plan category for notifications B. A specific notification type for maintenance plans C. A specific notification type that includes a task list D. A specific maintenance strategy for notifications
Answer: A
Question: 9
You customize an order type to release orders immediately upon creation Cheap Ryan Strome Hoodie , and you assign the order type to a maintenance item. How can a user override the automatic release of the order without creating a new order type? Please choose the correct answer. Response:
A. Select a maintenance planner group and set the Do Not Release Immediately indicator. B. Set the Do Not Release Immediately indicator in the task list header. C. Set the Do Not Release Immediately indicator in planning data for the maintenance item. D. Select a maintenance activity type and set the Do Not Release Immediately indicator.
Answer: C
Question: 10
For which business requirements must you use serial numbers? There are 2 correct answers to this question. Response:
A. To uniquely identify inventory material items B. To have a future option to track material items as pieces of functional locations C. To have a future option to track material items as pieces of equipment D. To have the option to track batches
Answer: AC
Question: 11
In which lifecycle scenarios can you use SAP Solution Manager? There are 3 correct answers to this question. Response:
A. Retirement B. Operations C. Implementation D. Optimization E. Scoping
Answer: BCD
Question: 12
Which of the following control characters is available in the edit mask of the structure indicator? Please choose the correct answer. Response: